Installation

1. Isolate the pipe

lrg_installation_one

2. Cut away old fitting

lrg_installation_two

3. Cleaning newly cut end

lrg_installation_three

4. Slide V33 into place on host pipe

lrg_installation_four

5. Fine tune positioning of V33 on host pipe

lrg_installation_five

6. Secure rear seal compression ring

lrg_installation_six

7. Position Amex-10 stainless steel ring

lrg_installation_seven

8. Prepare ring expander

lrg_installation_eight

9. Expand stainless steel ring

lrg_installation_nine

10. Pouring quick hardening resin

lrg_installation_ten

11. New PE pipe is bolted to V33

lrg_installation_eleven

12. New PE pipe length is welded into place

lrg_installation_twelve

13. The new pipe is connected

lrg_installation_thirteen